Owner: Humana

Construction Manager: Whiting Turner

Building: 10,000 sq ft

Completion: Fall 2009-Spring 2010

Electrical Contract: $ 650,000

Peak Man Power: 4

Scope: (2) 500 KVA UPS addition. Installation of 500 KVA UPS systems w/ maintenance bypass switch and battery backup. Insallation of (6) PDU’s for centers expansion, assistance w/ BIM coordination process. Installation of underground electrical primary to new building addtion. Furnish and install power and lighting which includes; Lightning protection, fire alarm, security installations.