WKU — Data Center

PROJECTS

WKU — Data Center

Owner: Wester Kentucky University

Construction Manager: Scott, Murphy, & Daniel

Building: 16,000 sq ft remodel into Tier II Data Center

Electrical Contract: $450,000.00 (Electrical equipment was owner furnished)

Peak Man Power: 12

Scope: Renovation of the existing space into a two-story 16,000 square foot area that will accommodate 64 client spaces in a secure structure for an integrative BGMU data Center. AES installed two 600 KW emergency generators, 1200 amp main, (3) 90 KW UPS Cabinets. All power & lighting was installed by AES.