Owner: Ford
Construction Manager: Durr Systems
Building: 283,000 sq. ft.
Completion: Fall 2015
Electrical Contract: $ 3,000,000.0
AES was awarded (3) individual projects from Durr Systems. The first project consist of (12) power feeder for new miscellaneous paint booths along with a 800 amp power feeder for a new chiller unit. The second project takes place in the existing paint facility, reworking existing power feeders, installing new control panels for existing paint booths and running control and power cable for new equipment. The third project is the installation of the new conveyor system for the entire 283,000 sq. ft. paint building. This conveyor is what transports the vehicles through the paint process.